Exciting Progress in the PAC and Fine Arts Addition
We made significant construction progress in the Performing Arts Center (PAC) and fine arts addition. Crews have been hard at work installing the interior finishes in these newly renovated spaces.
Demolition has begun in the technical education wing to refresh and modernize this space with new paint, ceiling tile, flooring, and accessories. In addition to renovated learning spaces, this phase of work will also repurpose an existing classroom into a new fitness center.
Updates on current and upcoming work
- Wrapping up finishing touches in the art and music wings
- Refinishing the existing wood floor in the PAC
- Painting the ceiling clouds in the PAC
- Painting and installing ceiling grid in the band room, scene shop, and music corridor
- Installing exterior signage in the new gym and fine arts entrances
Did You Know? The technical education wing renovations will include some exciting new learning spaces for students, such as a career and technical education (CTE) lab, video production space, and engineering design and drafting classrooms.
The PAC seating area is ready for paint.
Temporary walls in the corridor by the technical education wing separate staff and students from the ongoing construction.
This new flex classroom space was once part of the old gym.
The existing stage floor is being refinished.
Staff and students have moved back into the art classrooms